What Is PPV (Purchase Price Variance) ?

What is Purchase Price Variance (PPV) ?

Purchase Price Variance (PPV) is a measure used in cost accounting to quantify the difference between the standard cost of materials specified for production and the actual cost paid to acquire those materials. It’s a key indicator of how efficiently materials are being procured and managed within a manufacturing process.

Here’s a breakdown of Purchase Price Variance:

Calculation of PPV:

The formula for Purchase Price Variance (PPV) is typically:

PPV=(Standard Price−Actual Price)×Actual Quantitytext{PPV} = (text{Standard Price} – text{Actual Price}) times text{Actual Quantity}PPV=(Standard Price−Actual Price)×Actual Quantity

Interpretation of PPV:

Factors Affecting PPV:

  1. Changes in Material Costs: Fluctuations in raw material prices due to market conditions, inflation, currency exchange rates, etc.

  2. Supplier Performance: Variations in supplier pricing, discounts, rebates, and shipping costs.

  3. Quality of Materials: Higher-quality materials may come at a premium cost, affecting PPV.

  4. Volume Discounts: Failure to achieve volume discounts or changes in order quantities can impact PPV.

  5. Delivery Delays or Expedited Shipping: Additional costs incurred due to delays or expedited shipping methods can affect PPV.

Importance of PPV:

Example:

Let’s say a company’s standard cost for a particular raw material is $10 per unit, but due to market fluctuations, they ended up paying $12 per unit for 500 units of the material. The PPV would be calculated as:

PPV=($10−$12)×500=(−$2)×500=−$1,000text{PPV} = ($10 – $12) times 500 = (-$2) times 500 = -$1,000PPV=($10−$12)×500=(−$2)×500=−$1,000

In this case, the negative PPV of $1,000 indicates that the company paid $1,000 more for the material than expected based on standard costs, which could prompt further investigation into the reasons behind the variance and actions to mitigate it in the future.